Hi,
I have a task over a period of 14 weeks which I know will occur 2 days each
week.
However, I cant seem to use the recurring task option as i dont know
specifically WHICH days the task is occurring, just really that each week 2
man days will be used on the task.
any ideas what type of task to put into msp?

thanks for your help and thats to those who answered my post on this yesterday

Cheers
 
J

John M.

Set the task to fixed duration. Assign the resource at 40% units. By doing
so, you will want to assign the resource at no more than 60% to other tasks
during this same period (so that you can level/schedule the other tasks).

FYI - no need to re-post today. Somebody would have responded to your
thread from yesterday.