Hi -
Help! I am preparing a resource assignment list using the Resource Usage
View. I am copying and pasting from MS Project Resource Usage View to Excel.
I want to show for each person a list of their assignments listing WBS,
Resource Name, Remaining Work and Start date. I can get all of those columns
to show in Resource Usage View except for WBS. I can show ID from the Gantt
chart but not WBS. Is there any common field from the Gantt view that will
show in the Resource View even if I have to manually enter the WBS numbers so
I can get the WBS number to show?
Most appreciated.
Help! I am preparing a resource assignment list using the Resource Usage
View. I am copying and pasting from MS Project Resource Usage View to Excel.
I want to show for each person a list of their assignments listing WBS,
Resource Name, Remaining Work and Start date. I can get all of those columns
to show in Resource Usage View except for WBS. I can show ID from the Gantt
chart but not WBS. Is there any common field from the Gantt view that will
show in the Resource View even if I have to manually enter the WBS numbers so
I can get the WBS number to show?
Most appreciated.