Activity duration driven by other activities

P

pfdubz

How do I set up an activity whose duration is a function of a group of other
activitries. For instance, I I need to run a pump for as long as it takes to
pour a concrete structure that is controlled by other activities.
 
J

John

pfdubz said:
How do I set up an activity whose duration is a function of a group of other
activitries. For instance, I I need to run a pump for as long as it takes to
pour a concrete structure that is controlled by other activities.

pfdubz,
What you probably want is called a hammock task. Go to our MVP website
at, http://www.mvps.org/project/faqs.htm, and take a look at FAQ 19 -
Hammock tasks.

John