Actual Cost not being calculated

O

OVazqRodz

I'm working several schedules using global templates from my company. For
this particular project i've added ACTUAL WORK but the program is not
recognizing ACTUAL COST. It calculates REMAINING COST but not ACTUAL COST.
This only occurs in this specific project.

I've allready checked the COST RATE TABLES and these are correct.
 
F

FKhan

Check and see if the status date is set to something past the start date.
Also, check to make sure that earned value is being calculated on the correct
baseline. (tools - options - calculation tab - earned value button - select
correct baseline)
 
O

OVazqRodz

As I tried to verify your recomendations, I stumbled on a checkbox â–º "Actual
Costs are always calcualted by Microsoft Office Project" on
TOOLS/OPTIONS/CALCULATIONS tab.

There was the solution.

Thank you.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top