Actual Duration

D

Devendra Bhagat

Hi All,
One task is estimated to be completed in 5 days.
The resource actually completes the task in 10 days.
How can I enter the actual duration and also retain the original estimated
duration and cost?
How can I see the actual cost against the estimated cost?

Devendra
 
R

Rod Gill

Hi,

Before updating you schedule for the first time select:
Tools, Tracking, Save Baseline

This takes a copy of your schedule.

Now update actual duration as it actually happened. Compare actual against
baseline (estimated) by:
View, Table, Cost

--
Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 
M

Mike Glen

Hi Devendra ,

Welcome to this Microsoft Project newsgroup :)

You need to keep a baseline. Tools/Tracking/Save baseline.... Then you
can use the Tracking Gant view to see the effects of overrun.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on:)

Mike Glen
Project MVP
 
S

Sarah

Devendra,

When your schedule was approved by all necessary parties, you should
have baselined it. Saving a baseline is like saving a snapshot of the
plan at that moment in time. It provides for the historical
comparisons you are seeking. It saves all cost and work estimate
information in respective Baseline fields for later comparison against
actuals. You can save the baseline by clicking Tools>Tracking>Save
Baseline.

Sarah
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top