D
Devendra Bhagat
Hi All,
One task is estimated to be completed in 5 days.
The resource actually completes the task in 10 days.
How can I enter the actual duration and also retain the original estimated
duration and cost?
How can I see the actual cost against the estimated cost?
Devendra
One task is estimated to be completed in 5 days.
The resource actually completes the task in 10 days.
How can I enter the actual duration and also retain the original estimated
duration and cost?
How can I see the actual cost against the estimated cost?
Devendra