N
Norma
I am new to Microsoft project, when you enter a start and end
date for a task, is there a way to make it actual. Example, if I put
8/15/07 as start and 8/17/07 as end, it calculates it as 2 days and I
actually want to see 3 days since work is being done on the 15th, 16th &
17th. Thank you I have seached the help but cannot find it. It always
subtracts the begin date from the end date which reflects 1 day less. example
May 5 less May 1st = 4 days. I want my duration to show 5 days. Thank you
very much
date for a task, is there a way to make it actual. Example, if I put
8/15/07 as start and 8/17/07 as end, it calculates it as 2 days and I
actually want to see 3 days since work is being done on the 15th, 16th &
17th. Thank you I have seached the help but cannot find it. It always
subtracts the begin date from the end date which reflects 1 day less. example
May 5 less May 1st = 4 days. I want my duration to show 5 days. Thank you
very much