Thank You Steve.
So basically i can not have such task in my plan. Does that mean
"Reworks"
can not be planned. Then how usually people plan "Reworks"? As you
said,
the
reworks have to be a part of the original task. But then how will you
track
the effort spent on it? If add a task upon rework, then some one can
say
the
task was not planned. Any other better way ?
--
sr
:
What you're doing wrong is holding the idea that it is possible to do
a
task
without doing work <grin>. The duration of a task is the time
interval
over
which work takes place on it. If no work is taking place, there is no
task
and there is no duration. In fact, even zero-duration milestones
themselves
are pseudo-tasks and don't have any real existence - they're just a
reporting point, a waypoint on the map, like a roadside marker you
pass
while on a journey. Hence your attempt to create a task with 1 day
(or
any
other finite number) duration but a work effort of zero attempts to
create a
logical and physical impossibility - if no work is happening, there is
no
time interval being consumed. If you had a 5 day duration task
consuming
40
hours and at the end of that time you find it requires rework, the
number
of
physical man-hours the rework requires must be added to the total work
the
task required. You might not get paid for the rework or have budget
for
it,
but that's another issue entirely. Work is a measurable, observable
physical activity and as long as ANYTHING is happening, work is
happening
regardless of how or if it's accounted for in the allowed man-hour
budget.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Hi,
I have few task for Rework after every review but not aleays there
is a
rework to all tasks. When I update my plan with actual effort zero,
it
convert it to milestone task. I tried putting duration as a day and
work
as
0. but then the project do something automatically, either is clears
up
the
actual finish day and reduce the % complete. if I force % complete
to
100
or
put actual finish date, it convert the task to a milestone task.
Can someone help me, what i am doing wrong here.