L
lemonstown
When a milestone has been set and there are more days available than
required to finish a task it is possible to show those spare days as
float. When a milestone has passed and you have not completed a
particular tast as intended is it possible to show negative float in
your program to represent the number of days by which you have passed
the milestone?
Also, in a program I have start and finish columns which represent the
dates that were originally planned for the tasks to start and finish. I
also have columns showing actual start and actual finish. In the
tracking gantt I can enter an actual start date for a task that has
started but not yet finished. I cannot enter an actual finish because
the task is still in progress however is it possible to enter a new
planned finish date without the original planned finish date which would
affect my baseline.
required to finish a task it is possible to show those spare days as
float. When a milestone has passed and you have not completed a
particular tast as intended is it possible to show negative float in
your program to represent the number of days by which you have passed
the milestone?
Also, in a program I have start and finish columns which represent the
dates that were originally planned for the tasks to start and finish. I
also have columns showing actual start and actual finish. In the
tracking gantt I can enter an actual start date for a task that has
started but not yet finished. I cannot enter an actual finish because
the task is still in progress however is it possible to enter a new
planned finish date without the original planned finish date which would
affect my baseline.