M
Mike Kleiman
While analysing one of our MS Project 2007 plans, I noticed that one of the
resources has Actual Work entries for future dates - all the way through
April, 2008. This doesn't seem possible and definately isn't legitimate e.g.
he hasn't worked those hours yet and they shouldn't be in the plan as actuals
- IMHO.
We do have a timesheet tool that automatically updates daily actuals onto
our plans and my first thought was that this individual processed future
timesheets and somehow got them through the approval process and got the
hours progressed down to the plan. I ruled this out because this individual
is not ahead on his timesheets.
Microsoft Project automatically distributes planned work but does it do
anything automagically that might explain how future actuals could be present
in the plan?
I appreciate your help.
Mike Kleiman
resources has Actual Work entries for future dates - all the way through
April, 2008. This doesn't seem possible and definately isn't legitimate e.g.
he hasn't worked those hours yet and they shouldn't be in the plan as actuals
- IMHO.
We do have a timesheet tool that automatically updates daily actuals onto
our plans and my first thought was that this individual processed future
timesheets and somehow got them through the approval process and got the
hours progressed down to the plan. I ruled this out because this individual
is not ahead on his timesheets.
Microsoft Project automatically distributes planned work but does it do
anything automagically that might explain how future actuals could be present
in the plan?
I appreciate your help.
Mike Kleiman