O
osucowboy
On a weekly basis I:
1) key the actual hours resources worked into the schedule
2) set the project status date to the new date (one week out)
3) update project selecting the "reschedule uncompleted work to start after"
and "entire project" radio buttons and accept the default date which is the
new project status date
Here's the question:
Why does MS Project sometimes show actual work in the future from the status
date? I do not key hours in the future. Does anyone know a valid reason why
this would occur, or is there an option in MS Project that is causing this?
Thanks in advance.
Some of the tasks are fixed work, some are fixed duration. I am using 2002
professional.
1) key the actual hours resources worked into the schedule
2) set the project status date to the new date (one week out)
3) update project selecting the "reschedule uncompleted work to start after"
and "entire project" radio buttons and accept the default date which is the
new project status date
Here's the question:
Why does MS Project sometimes show actual work in the future from the status
date? I do not key hours in the future. Does anyone know a valid reason why
this would occur, or is there an option in MS Project that is causing this?
Thanks in advance.
Some of the tasks are fixed work, some are fixed duration. I am using 2002
professional.