Actual worked hour (daily)

J

Johnny

How can I change from weekly to daily for the tasking hours worked. (PWA)

Thanks

Johnny
 
D

Dale Howard

Johnny --

You will need to get your Project Server administrator to change your
company's settings for tracking progress. Here's what he/she will need to
do:

1. Log into Project Web Access as Administrator
2. Click the Admin menu
3. Click the Customize Microsoft Project Web Access link
4. In the sidepane on the left, click the Tracking Settings link
5. In the "Specify the default method for reporting progress on tasks"
section, select the "Hours of work done per day or per week" option
6. In the "Time period settings" section, select the "Resources should
report their hours worked every day" option
7. Click the Save Changes button

Once this has been done by your Project Server administrator, you will then
need to open each of your projects and republish the assignments for each
project. To do this, click Collaborate - Publish - Republish Assignments,
then click OK. This will change everyone's timesheets to allow them to
enter their hours on a daily basis, rather than a weekly basis. Hope this
helps.
 
J

Johnny

Thanks


Dale Howard said:
Johnny --

You will need to get your Project Server administrator to change your
company's settings for tracking progress. Here's what he/she will need to
do:

1. Log into Project Web Access as Administrator
2. Click the Admin menu
3. Click the Customize Microsoft Project Web Access link
4. In the sidepane on the left, click the Tracking Settings link
5. In the "Specify the default method for reporting progress on tasks"
section, select the "Hours of work done per day or per week" option
6. In the "Time period settings" section, select the "Resources should
report their hours worked every day" option
7. Click the Save Changes button

Once this has been done by your Project Server administrator, you will then
need to open each of your projects and republish the assignments for each
project. To do this, click Collaborate - Publish - Republish Assignments,
then click OK. This will change everyone's timesheets to allow them to
enter their hours on a daily basis, rather than a weekly basis. Hope this
helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top