F
Fawaz
I have the following case:
Task Name : Installation
Duration: 6d
Start Date: Mon 13/02/06
End Date:
Base line Cost: 10,000 $
Status Date: Tue 14/02/06
Resources: No Resources assigned
What is the deference between the two fields ACWP and Actual Cost?
My observation is that: when the % Complete (Task Progress in gantt chart)
less than the statues date line (in gantt chart) both ACWP and Actual Cost
are same value. But when the progress exceeds the statues date line (in gantt
chart), ACWP gave figures that I couldn’t understand.
e.g.Based in the given information in the top
% Complate 20% Actual Cost= 4,000 ACWP =4,000
% Complate 30% Actual Cost= 5,000 ACWP =5,000
% Complate 45% Actual Cost= 6,000 ACWP = 5,222.22
So, What is ACWP, how is it calculated and what is the explaination for the
last given figure
Any help are appreciated
Thanks.
Task Name : Installation
Duration: 6d
Start Date: Mon 13/02/06
End Date:
Base line Cost: 10,000 $
Status Date: Tue 14/02/06
Resources: No Resources assigned
What is the deference between the two fields ACWP and Actual Cost?
My observation is that: when the % Complete (Task Progress in gantt chart)
less than the statues date line (in gantt chart) both ACWP and Actual Cost
are same value. But when the progress exceeds the statues date line (in gantt
chart), ACWP gave figures that I couldn’t understand.
e.g.Based in the given information in the top
% Complate 20% Actual Cost= 4,000 ACWP =4,000
% Complate 30% Actual Cost= 5,000 ACWP =5,000
% Complate 45% Actual Cost= 6,000 ACWP = 5,222.22
So, What is ACWP, how is it calculated and what is the explaination for the
last given figure
Any help are appreciated
Thanks.