ACWP Does Not Equal Cummulative Cost

J

Jimmy

Settings: MSP2003 SP2
Manual Costs calculations (both boxes unchecked)
Task View, custom EV table shows ACWP, Actual Cost, and Cummulative Cost.
Actual Cost is manually keyed into the task view by month.

In the task pane, right side, when I use the arrow keys to move around, the
value of ACWP changes when I arrow over it. If I press F9 the value of ACWP
returns to the value of Cummulative Cost. THen when I arrow away from the
"cell" the value of ACWP drops. Once it changes, it stays put until I press
f9 again.

The value of ACWP holds constant if I insert the ACWP column into either
task or gantt view.
 