D
DavidR
I am entering Actual Cost manually, and have a status date set in project
information. For most of the task the ACWP equals the amount I am putting in
for Actual Cost as expected. But for some of the task the number is slightly
different. I can not figure out why it is equal for some tasks and different
for others, and have checked everything I can think of. Any suggestions?
information. For most of the task the ACWP equals the amount I am putting in
for Actual Cost as expected. But for some of the task the number is slightly
different. I can not figure out why it is equal for some tasks and different
for others, and have checked everything I can think of. Any suggestions?