You can always make a meeting a milestone with no predecessors or successors
and then key the date. Not advisable however.
Usually, there are given predecessors to a meeting such as drawings
complete, specification complete, plans ready for approval, etc. In this
case, if the meeting must happen on a given day, you are faced with a couple
of choices.
All the choices for a constraint type are available on the Advanced Tab of
the Task Properties. Double click the task, then select the Advanced tab.
Your options there are to select a Constraint Type from the drop down, and
then specify a date such as "Finish No Later Than" ... December 31, 2007.
Alternatively, you may choose a deadline date from the same tab.
Be careful on selecting constraint types since they can be routinely
violated with predecessor logic. Project will warn you.
You can see if tasks have constraints or violated deadlines by a visual
display in the indicators column.
--
If this post was helpful, please consider rating it.
Jim
It''s software; it''s not allowed to win.
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project