Adding a delay / lag in an activity that has started

D

Dale N

I am using MS Project Professional 2003. How do I add a delay in an activity
that has already started so that the actual duration of the activity does not
include the period that the activity was delayed?
 
G

Gérard Ducouret

Hello Dale,

Have you tried :

Select the task in question then,

Tools / Tracking / Update Project / Reschedule uncompleted work to start
after.... (set a date)
Click the "Selected tasks" option
OK

Gérard Ducouret
 
D

dwolf

Dale,

You will want to check your options to ensure that the "split
in-process tasks" is selected. This can be found in the Schedule tab
under Tools=> Options.

You can also right-click the bar associated with the task and select
Split Task and drag the ends of the split to match your delay.

I hope this helps you.

--dwolf
 
D

Dale N

Thanks Gerard... appreciate the help!

Gérard Ducouret said:
Hello Dale,

Have you tried :

Select the task in question then,

Tools / Tracking / Update Project / Reschedule uncompleted work to start
after.... (set a date)
Click the "Selected tasks" option
OK

Gérard Ducouret
 