Adding Text to links between Tasks

B

BPM

Hi All

is it possible to add text to links between two tasks? If Yes, how do I do
that?

I would like to add "Yes" or "No". I want to make a project plan with
different paths, depending on decisions at milestones.

Regards

Heinz
 
J

John

BPM said:
Hi All

is it possible to add text to links between two tasks? If Yes, how do I do
that?

I would like to add "Yes" or "No". I want to make a project plan with
different paths, depending on decisions at milestones.

Regards

Heinz

Heinz,
I assume you want to put labels, such as "yes" and "no", on the link
lines between tasks. Well, it probably can be done but not in Project
itself. Although Project has some good graphic capabilities for schedule
Gantt type charts, it is not intended as a do-all graphics package. In
order to do what I assume you want, you will need to export the Gantt
information to another more graphic intensive application - perhaps
Visio, PowerPoint or other graphic application.

Hope this helps.
John
Project MVP
 