J
jkazan
Hello
I use columns (Work, % work complete, Start task, Finish task) for
machine.
The day of finished task is calculated automatically.
In the same raw I'd like to add the same columns (work-number of hours,
% work complete, start, finish) for man which writting a programme for
machining. The name of programmer, % work complete and start date I will
type in project manually, finish day must bel calculated automaticcaly.
I add that 1machine works 24ht per day, second 16ht per day, part of
machines works in saturday and sundey. programmer works 8ht per day,
5day in week, ALWAYS.
How to do it? Which fileld names I shuld use? How calculate finish
date?
Regards
I use columns (Work, % work complete, Start task, Finish task) for
machine.
The day of finished task is calculated automatically.
In the same raw I'd like to add the same columns (work-number of hours,
% work complete, start, finish) for man which writting a programme for
machining. The name of programmer, % work complete and start date I will
type in project manually, finish day must bel calculated automaticcaly.
I add that 1machine works 24ht per day, second 16ht per day, part of
machines works in saturday and sundey. programmer works 8ht per day,
5day in week, ALWAYS.
How to do it? Which fileld names I shuld use? How calculate finish
date?
Regards