Adjusting Resource Allocations as availability Changes

R

RonnBlack

I have a project that has several resources that were originally assigned at
100%. These resources are now only available 50% of the time.

What is the best way to adjust their allocation to the tasks that they are
assigned?
 
S

Steve House [Project MVP]

Go to each task the resource is assigned to and edit his assignment down
from 100% to 50% You can do it in one operation by selecting multiple
tasks.
 
J

Jan De Messemaeker

Hi Ronn,

Click the Assign resources button on the toolbar
Select all tasks
Select the resource
Click replace
Again select the resource, specifying 50%.
HTH
 