Greetings All;
Background.
I have a resource pool with many resources from many different groups.
I have 9 projects, with tasks, with resources from the resource pool
assigned to the tasks.
Many of the resources have been assigned to multiple tasks on multiple
projects.
A Master Project has been established to view all 9 projects.
With the Master Project open, in resource usage view, I can see all of the
tasks, and projects a resource is assigned to. And, fortunatley MSP will
provide a roll up of the resource allocation, by task, by project for the
period of time selected.
Now the challenge. I need to be able to see (and graph) how much a specific
resource is allocated to a specific project. In the Master Project resource
usage view, the allocation rollup is by resource, not by project.
For example, lets say "Andy" is assigned to 4 tasks on Project A, 5 tasks on
Project B, and 3 taks on Project C. In the Master Project resource usage
view, I can see all of Andy's allocations to the 12 tasks over three
projects. Is is possible to have MSP insert a summary to show the allocation
by project instead of task?
I've tried various groupings but somehow can't find a way to summarize
allocations by project.
MSP2003 pro sp2.
All suggestions are appreciated.
Background.
I have a resource pool with many resources from many different groups.
I have 9 projects, with tasks, with resources from the resource pool
assigned to the tasks.
Many of the resources have been assigned to multiple tasks on multiple
projects.
A Master Project has been established to view all 9 projects.
With the Master Project open, in resource usage view, I can see all of the
tasks, and projects a resource is assigned to. And, fortunatley MSP will
provide a roll up of the resource allocation, by task, by project for the
period of time selected.
Now the challenge. I need to be able to see (and graph) how much a specific
resource is allocated to a specific project. In the Master Project resource
usage view, the allocation rollup is by resource, not by project.
For example, lets say "Andy" is assigned to 4 tasks on Project A, 5 tasks on
Project B, and 3 taks on Project C. In the Master Project resource usage
view, I can see all of Andy's allocations to the 12 tasks over three
projects. Is is possible to have MSP insert a summary to show the allocation
by project instead of task?
I've tried various groupings but somehow can't find a way to summarize
allocations by project.
MSP2003 pro sp2.
All suggestions are appreciated.