Admin Project Questions

E

eswb10

I have followed the many discussions regarding using admin projects
following the procedures that Dale Howard recommends. My questions are:

(1) If I create an admin project using that process, should that
project be published as a regular enterprise project, or should it be
published using the "Administrative Project" switch on the Save File
dialog box?

(2) If published as a regular enterprise project, the tasks will
disappear after some time using the "Current Tasks" setting in the task
sheet. I know that's a process and training issue. But how do we
prevent an overdue task notification from being sent if a resource
doesn't use an admin task category?


TIA -


Mark
 
Top