Arlo
Hi,
we experiencing some trouble with administrative projects. although they are
unplanned, when an employee books 20 hours in the webaccess Project does the
following:
work=0, remaining work=20 AND shows a finish date (when using 8 hrs a day
that will be approximately 20/8 days later).
Is that normal behaviour? It seems to be, but it also does raise questions