H
Howard
Hi,
I'm trying to assign available work hours to resources within a project's
task in MS Project 2000. I'm only tracking tasks and time, not $$ costs.
For example, task 1, I've assigned Jane to it, and she's been given 12 hours
per year (long range project lasting over 2 1/2 years). How can I assign
Jane just the 12 hrs.? Do I need to figure out manually what the % is?
Thanks, Howard
I'm trying to assign available work hours to resources within a project's
task in MS Project 2000. I'm only tracking tasks and time, not $$ costs.
For example, task 1, I've assigned Jane to it, and she's been given 12 hours
per year (long range project lasting over 2 1/2 years). How can I assign
Jane just the 12 hrs.? Do I need to figure out manually what the % is?
Thanks, Howard