L
Leo R
Would like to know if there is another way of linking a task in one project
with that of another?
We have just implemented Enterprise Project Management using Project Server
2003. To link a task in one project to that of another, we were taught to
type the location of the task of the external project in the predecessor
collumn using the following syntax:
<>\name of the project to be connected to.published\position of the
target task
You can see that the process above requires typing the name of the project
which is open to many errors. Is there a better way to do this?
Thank you in advance.
with that of another?
We have just implemented Enterprise Project Management using Project Server
2003. To link a task in one project to that of another, we were taught to
type the location of the task of the external project in the predecessor
collumn using the following syntax:
<>\name of the project to be connected to.published\position of the
target task
You can see that the process above requires typing the name of the project
which is open to many errors. Is there a better way to do this?
Thank you in advance.