Apply default working hours retrospectively

A

Amal

Hi,

I have made a project plan with N resources each working
for 7 hours a day (an oversight ofcourse!). I would like
to retrospectively update the working hours of all
resources for all days to 8 hours per day?

What is the best way to do this without having to
recreate the plan / resources?

Thanks in advance for the reply.

Amal
 
M

Mike Glen

Hi Amal,

Welcome to the Microsoft Project newsgroup :)

Please make sure you understand FAQ Item: 5. Default Working Hours.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on:)

Mike Glen
Project MVP
 
G

Gérard DUCOURET

Hello Amal,
First of all, you copy all your Duration field in a personal field like Text1.
Then you go to Tools / Options / Calendar : Hours per day : 8; hours per week : 40
Then you copy back your Text1 durations in the Duration field.

Hope this help,

Gérard Ducouret
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top