C
Chalrie57
Let's say I am painting a car in a shop and I have three painters.
have my cost and my resources all filled out. The Gantt Chart is fine
then for no reason the hours needed to not match the days it will tak
to complete a project. Example: I have 6 hours per day per person,
have a 24 hour project with three people so the hour shows "8" thi
should be done in 1.3 days but the dates show Thursday 6/3 to Tuesda
6/8 four working days. I am guessing I have checked a box I should no
have.
Any ideals?
Thanks,
Charli
have my cost and my resources all filled out. The Gantt Chart is fine
then for no reason the hours needed to not match the days it will tak
to complete a project. Example: I have 6 hours per day per person,
have a 24 hour project with three people so the hour shows "8" thi
should be done in 1.3 days but the dates show Thursday 6/3 to Tuesda
6/8 four working days. I am guessing I have checked a box I should no
have.
Any ideals?
Thanks,
Charli