Assign a resource for only part of a task.

S

Suliman

I want to assign Jose to a task that will take four days to complete but I
only want to assign Jose to two of the days. I don't want to assign him part
time to the entire task where he would be on it for all four days at 50%
usage, but rather for two days at 100% and two days not assigned to that task.
 
J

Jan De Messemaeker

Hi Suliman,

If the task is fixed Units, simply assign him 100% then in the task Usage
view change the assignmen(t's work to 2 days.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
Suliman said:
I want to assign Jose to a task that will take four days to complete but I
only want to assign Jose to two of the days. I don't want to assign him part
time to the entire task where he would be on it for all four days at 50%
usage, but rather for two days at 100% and two days not assigned to that
task.
 