Assign Resource Pool

K

Karen

I created a resource pool and saved it as a file. Then I created a template
for my projects. How do I assign the resource pool to my template?

Thank you
 
G

Gérard Ducouret

Hello Karen
Open bothe the resource pool and the schedule project.
in the schedule plan : Tools / Resource sharinf / Share resources...
Use resources From....

Gérard Ducouret
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question