B
benderbends
i have 6 tasks that run for various durations with various prioritie
and various start dates.
I currently have a resource (designer) applied to all of these tasks a
100%.
What i want to be able to do is assign the resource at a specific % fo
a set amount of Days.
For example....Days 1-20 i will have 500% Designers to distribute. Bu
Days 21-30 I will have 200%, and Days 31-40 I will have 800%.
Is there a way to do this?
I tried assigning each task higher and lower amounts, but if the tas
overlaps these different day groups...then i can adjust the % withou
effecting earlier durations
and various start dates.
I currently have a resource (designer) applied to all of these tasks a
100%.
What i want to be able to do is assign the resource at a specific % fo
a set amount of Days.
For example....Days 1-20 i will have 500% Designers to distribute. Bu
Days 21-30 I will have 200%, and Days 31-40 I will have 800%.
Is there a way to do this?
I tried assigning each task higher and lower amounts, but if the tas
overlaps these different day groups...then i can adjust the % withou
effecting earlier durations