Hello, Is it possible to get a page kind of like the resource usage sheet
where tasks can be assigned to resources. It is so easy to assign resources
to tasks but my tasks can be done whenever, it is my resources I need to
schedule across several projects without over allocation.
 
M

Manmeet Chaudhari

Hi
You can use the resource assignment view.
Goto resource pool select resource and then click on view resource assignment.

You will be able to view but not change
Hope this helps
 
J

Jan De Messemaeker

Hi,

I do not know a resource assignment view.
The resource assignment window is not accessible from any resource view.
Greetings,
 