First, I have to assume each task will have only one resource assigned..
This being accepted, here is a way (by no means easy)
Set up number of customized flag fields as follows
Flag1 formula: true if resourcenames is Resource1
Flag2 formula: true if resourcenames is Resource2
etcetera.
Then read http://www.mvps.org/project/faqs.htm
Faq 31. Customizing task bars
HTH