Assigning a resource to a task that has a predecessor changes finish time.
Consider a scenario where my Project Calendar has working timings from 9:30
AM to 12:00 AM and 12:30 AM to 6:00 PM. Same pattern is followed for the
resource calendar.
I add 4 tasks. Link 1 to 3 and 2 to 4 with F-S links (0 day link lag).
Now when I assign a single resource to Task 1, the task finish date does not
change (its still 6:00 PM). However, assigning the resource to Task 3 or Task
4 (which have predecessors), the finish time changes to 10:30 AM from 6:00 PM.
Can someone explain me this behavior.
Note: One has to change the Date Format in the View Tab as seen from Tools
--> Options in MSP to show the time component as well.
Consider a scenario where my Project Calendar has working timings from 9:30
AM to 12:00 AM and 12:30 AM to 6:00 PM. Same pattern is followed for the
resource calendar.
I add 4 tasks. Link 1 to 3 and 2 to 4 with F-S links (0 day link lag).
Now when I assign a single resource to Task 1, the task finish date does not
change (its still 6:00 PM). However, assigning the resource to Task 3 or Task
4 (which have predecessors), the finish time changes to 10:30 AM from 6:00 PM.
Can someone explain me this behavior.
Note: One has to change the Date Format in the View Tab as seen from Tools
--> Options in MSP to show the time component as well.