A
Andy Lenik
Hi All
Can anyone tell me how I can assign a resource to a task that another
resource is already working on, after the first resource has completed
their first task?
E.g.
Task 1 is 5 days' effort.
Task 2 is 10 days' effort.
Resource A begins work on task 1, and at the same time resource B
begins work on task 2.
At the moment the duration of task 2 will be 10 days.
What I want to say is that on completion of task 1 resource A is free
to work on task 2 with resource B... so really (unless task 1 takes
longer than expected) the duration of task 2 should be 7½ days.
Any ideas? I didn't want to assign resource A to task 2 as a lower %
of the work, as I want to say that they are working on these tasks
100% of their time - and also benefit from the fact that task 1 could
finish early / late and for the duration of task 2 to reflect the
changes.
Thanks in advance, Andy.
Can anyone tell me how I can assign a resource to a task that another
resource is already working on, after the first resource has completed
their first task?
E.g.
Task 1 is 5 days' effort.
Task 2 is 10 days' effort.
Resource A begins work on task 1, and at the same time resource B
begins work on task 2.
At the moment the duration of task 2 will be 10 days.
What I want to say is that on completion of task 1 resource A is free
to work on task 2 with resource B... so really (unless task 1 takes
longer than expected) the duration of task 2 should be 7½ days.
Any ideas? I didn't want to assign resource A to task 2 as a lower %
of the work, as I want to say that they are working on these tasks
100% of their time - and also benefit from the fact that task 1 could
finish early / late and for the duration of task 2 to reflect the
changes.
Thanks in advance, Andy.