F
FiguringItOut
Hi all - Can someone explain how Project divides work when you add
additional resources to a fixed-unit task? I understand relatively
the well the idea of duration = work*units and I get the calculations
easily when the situation is clear:
1 resource on a 6 day (48h) task - and assign an additional resource
at 100% and the work is divided in 2 - 3 day duration each working
24h.
But for instance if you add that second resource at 50% (or heaven
forbid a third at 25%) - how does the redistribution of work calculate
- does Project first use the units available to divide the total work
for each resource? if so how does it decide how much work to give
each? does it then assign max per day for each resource until work
runs out and that is what determines the duration? I feel like I am
on the edge of understanding it but its fuzzy and I don't feel like I
get consistent results as I experiment with various assignments -
maybe someone can offer some clarity on the calculation rules/process
Project is using for distribution of work when assigning additional
resources to fixed-unit/effort driven tasks.
Thanks in advance for any insight/help you have to offer.
Sincerely,
Lizandra
additional resources to a fixed-unit task? I understand relatively
the well the idea of duration = work*units and I get the calculations
easily when the situation is clear:
1 resource on a 6 day (48h) task - and assign an additional resource
at 100% and the work is divided in 2 - 3 day duration each working
24h.
But for instance if you add that second resource at 50% (or heaven
forbid a third at 25%) - how does the redistribution of work calculate
- does Project first use the units available to divide the total work
for each resource? if so how does it decide how much work to give
each? does it then assign max per day for each resource until work
runs out and that is what determines the duration? I feel like I am
on the edge of understanding it but its fuzzy and I don't feel like I
get consistent results as I experiment with various assignments -
maybe someone can offer some clarity on the calculation rules/process
Project is using for distribution of work when assigning additional
resources to fixed-unit/effort driven tasks.
Thanks in advance for any insight/help you have to offer.
Sincerely,
Lizandra