If I assign more than one individual resource to a task, MS Project
schedules assuming that the resources can work independantly of one another.
How can I assign more than one resource to a task and indicate that those
resources need to work as a group on that task, for example if one resource
is on holiday then the task can't continue (with the other resources) until
that one returns from holiday?
Hope someone can help me on this one!