R
Rex O
When a task has the work specified and there are two or more resources
assigned to the task and the first resource is assigned only 10% of the time,
the task duration becomes 10xWork time. It seems like a bug to me, please
confirm and/or sugest alternative solution. Problem does not happen if we
specify the duration and leave the work field blank.
--
Thanks for the help,
Best Regards,
RexO
assigned to the task and the first resource is assigned only 10% of the time,
the task duration becomes 10xWork time. It seems like a bug to me, please
confirm and/or sugest alternative solution. Problem does not happen if we
specify the duration and leave the work field blank.
--
Thanks for the help,
Best Regards,
RexO