Assigning Generic resources

  • Thread starter Carolyn in Fredericton NB
  • Start date
C

Carolyn in Fredericton NB

Good Day
I am seeing results in Project 2003 that I had not expected when trying to
allocate generic resources to tasks.
A bit of background first
The project that I am on is using an iterative approach, and future releases
are planned at increasingly higher level of detail depending on how far out
it is.
I know for Release x, I have 3 streams of work, with a set group of
developers for each stream; 3 in streams 1 and 3, and 5 developers in Stream
2. I also know at a high level task level how much work we have for each of
the 3 streams; eg, 500 hours development work for Stream 1, 900 hours for
Stream 2 and 550 for Stream 3. I added 3 generic resources (Stream 1, Stream
2, and Stream 3 with resource availability units of 300%, 500% and 300%
respectively). I assigned the resources to the tasks, but Project is only
assigning the work at 100%. I would not think that I would have also have to
change the resource assignment in the actual task to pick up either 300% or
500% according to the stream it is associated with? When I have multiple
tasks that I assign a group to, it seems to allocate up to the percentage
expected, but not when I allocate a group to 1 task - it is like it does not
want to allocate the task across multiple resources. I am just wondering if
having a generic resource showing as 300% available and then going into the
task itself and switching to 300% will cause a problem? I am just trying at
this point to get a view to end dates on releases based on large chunks of
work taht have not been broken down into more detailed tasks yet.
 
M

Mike Glen

Hi Carolyn,

Welcome to this Microsoft Project newsgroup :)

Project cannot possibly know how many resources to assign to each task. That's your job. So, for generic resources, if you want 3 assigned then assign 300%.

FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials



Good Day
I am seeing results in Project 2003 that I had not expected when trying to
allocate generic resources to tasks.
A bit of background first
The project that I am on is using an iterative approach, and future releases
are planned at increasingly higher level of detail depending on how far out
it is.
I know for Release x, I have 3 streams of work, with a set group of
developers for each stream; 3 in streams 1 and 3, and 5 developers in Stream
2. I also know at a high level task level how much work we have for each of
the 3 streams; eg, 500 hours development work for Stream 1, 900 hours for
Stream 2 and 550 for Stream 3. I added 3 generic resources (Stream 1, Stream
2, and Stream 3 with resource availability units of 300%, 500% and 300%
respectively). I assigned the resources to the tasks, but Project is only
assigning the work at 100%. I would not think that I would have also have to
change the resource assignment in the actual task to pick up either 300% or
500% according to the stream it is associated with? When I have multiple
tasks that I assign a group to, it seems to allocate up to the percentage
expected, but not when I allocate a group to 1 task - it is like it does not
want to allocate the task across multiple resources. I am just wondering if
having a generic resource showing as 300% available and then going into the
task itself and switching to 300% will cause a problem? I am just trying at
this point to get a view to end dates on releases based on large chunks of
work taht have not been broken down into more detailed tasks yet.
 
C

Carolyn in Fredericton NB

Hello Glen
Thanks for your response
So, I misunderstood the availability percentage under the resource
information sheet? I had interpretted that if I had a resource type available
at 300%, and assigned to a task, that all available units for that group were
applied to the task.
Thanks a lot
 
J

Jan De Messemaeker

Hi,

I think you understood well.
It's just that when you assign a resoruce to a task (generic or whatever)
and you do not specify the assignment unis, Project allocates the resource
as
"Max Units or 100%, whichever is lower"
So when assigning you will have to specify any nomber over 100%.

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Carolyn in Fredericton NB"
 
M

Mike Glen

You're welcome, Carolyn Yes - the Max Units is the measure Project uses to report over allocations.

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials


Hello Glen
Thanks for your response
So, I misunderstood the availability percentage under the resource
information sheet? I had interpretted that if I had a resource type available
at 300%, and assigned to a task, that all available units for that group were
applied to the task.
Thanks a lot
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top