Assigning Resources at 50%

S

SheriTingle

Hi and thanks for the help. I am using Project 2007. When I assign one
resource at 50% it automatically assigns all of the resources at the same
time and at 100%. So, I get one person assigned as I want at 50% but all
others come along at 100%. I am using the button with two heads to do this
assigning. HELP~ Thanks!
 
J

Jim Aksel

Try Window/Split...
The resources will show in the bottom pane where you can make necessary
adjustements to the assignment %. Additionally, resources may be assigned
one at a time.
--
If this post was helpful, please consider rating it.

Jim
It''s software; it''s not allowed to win.

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top