Wile Coyote
I am setting up a production schedule and i would like to be able to
assign some of the equipment as a resource so it does not become
overbooked. If i have machine A and machine B and Machine C some task are
only able to be done on machine A Some only on B etc. Some operations are
able to run on either machine A, b or C. can I group these machines or
assign them is some way that project will automaticly schedule the one that
has the most open time.
TIA for any help you have to offer
Thanks,
WC