Robin Roe
Hi
Just wondering if anyone knows the easiest way of doing the following.
Fixed duration task of 5 days
2 Resources to be assigned
Resource 1 will be 100% for the 5 days - no problems there
Resource 2 will be 100% (or 8 hrs per day) for days 2, 3 & 4 (24 hrs in Total)
Under the 'Task Usage - Usage' view it is possible to put 0 hrs in day 1 and
day 5 for Resource 2, which is fine for the simple example above, but not
very practical if the task is a year long.
I have also tried using the Start and Finish date options under 'Assignment
Information' dialog box but this alters the task duration.
Any help is much appreciated.
Thanks
Just wondering if anyone knows the easiest way of doing the following.
Fixed duration task of 5 days
2 Resources to be assigned
Resource 1 will be 100% for the 5 days - no problems there
Resource 2 will be 100% (or 8 hrs per day) for days 2, 3 & 4 (24 hrs in Total)
Under the 'Task Usage - Usage' view it is possible to put 0 hrs in day 1 and
day 5 for Resource 2, which is fine for the simple example above, but not
very practical if the task is a year long.
I have also tried using the Start and Finish date options under 'Assignment
Information' dialog box but this alters the task duration.
Any help is much appreciated.
Thanks