assigning resources to task

B

Bobby Castor

How do I assign the same resource more than once in the same task? ie: 2 laborer's for task "A"
 
J

John Beamish

Assign the resource at 200%.

1. Double-click on the task
2. Click on the Resource tab
3. Select the resource
4. Enter 200%



How do I assign the same resource more than once in the same task? ie:
2 laborer's for task "A"



--
 