How do I assign the same resource more than once in the same task? ie: 2 laborer's for task "A"
B Bobby Castor May 28, 2004 #1 How do I assign the same resource more than once in the same task? ie: 2 laborer's for task "A"
J John Beamish May 28, 2004 #2 Assign the resource at 200%. 1. Double-click on the task 2. Click on the Resource tab 3. Select the resource 4. Enter 200% How do I assign the same resource more than once in the same task? ie: 2 laborer's for task "A" Click to expand... --
Assign the resource at 200%. 1. Double-click on the task 2. Click on the Resource tab 3. Select the resource 4. Enter 200% How do I assign the same resource more than once in the same task? ie: 2 laborer's for task "A" Click to expand... --