D
Devendra Bhagat
Hi,
I have a task on which one resource is going to spend 15 days. Additionaly
resource2 is also to spend 1 day on the same task. If I enter 8 hrs for
resource2 then it is not accepting on the day on which he has actually
worked but takes it somewhere in Feb 2004. How do i solve this problem?
Thanks
Devendra
I have a task on which one resource is going to spend 15 days. Additionaly
resource2 is also to spend 1 day on the same task. If I enter 8 hrs for
resource2 then it is not accepting on the day on which he has actually
worked but takes it somewhere in Feb 2004. How do i solve this problem?
Thanks
Devendra