Assigning Resources

D

Devendra Bhagat

Hi,

I have a task on which one resource is going to spend 15 days. Additionaly
resource2 is also to spend 1 day on the same task. If I enter 8 hrs for
resource2 then it is not accepting on the day on which he has actually
worked but takes it somewhere in Feb 2004. How do i solve this problem?

Thanks

Devendra
 
J

Jan De Messemaeker

Hi Devendra,

You solve this mby making sure the second resource is available for work
right now.
Go have a look at resource Information, the resource probaly has a contoured
availability.
(For instance, 50% available between such ans such other date)
If that is the case, be aware that the periods not mentionned in this list
default to 0% availability.

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA