bmcqueen
Hi,
I have discovered a feature of Project 2007 that is causing me som
problems. I want to assign an engineer and access to a tool (so tha
no-one else can use it). However if I assign both as work resources an
my engineer is on holiday, it schedules for the tool to do 50% of th
work on its own. How can I ensure that both are required simultaneousl
to perform the task.
Any help with this would be appreciated