Michael
When I put in work, duration, and the resource Project rightfully assigns say
10% of that resource to the task.
But when I put in another task specifying work, duration, and the resource
it will do the same for the second task 10% but then the resource is
overallocated because it didnt recalculate the first task % when I level it.
It seems that the % assigned to the first task would need to change because
of the new commitment.
Maybe I am just not thinking of it right?
10% of that resource to the task.
But when I put in another task specifying work, duration, and the resource
it will do the same for the second task 10% but then the resource is
overallocated because it didnt recalculate the first task % when I level it.
It seems that the % assigned to the first task would need to change because
of the new commitment.
Maybe I am just not thinking of it right?