Automated allocation depending on group

X

Ximera

Hi,

I have a project with defined tasks relations. I want to specify
several working groups like "Developers", "Testers", "Designers" etc.
and specify group, duration and required number resources (e.g. task1
requires 2 days and 2 persons from "Developers") for every task. After
that I want to automatically level all tasks depending on number of
resources in each group.

Can I do that somehow in MSP (2003 Professional)?

Thank you.
Eugene
 
J

Jim Aksel

Tools/View Resource Sheet.
Instead of entering names - Bob, Ted, Carol, Alice... enter resource groups
such as Sr SW Developer, Test Engineer, QA Inspector. In the max units
column enter the total number of that resource available. 100%=1 head,
200%=2 heads.

When all tasks are in, properly linked, and resources assigned-
Tools/Level Resources....
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Similar Threads


Top