Y
ycchehadeh
I have 5 tasks w/ various durations and 3 resources - all of whom are
equivalent in skills. Each task requires one resource only (no
sharing). There are depedencies among the tasks. Is it possible for
MS Project to figure out the best task-resource allocation to optimize
for the earliest project finish time w/o me having to assign each task
to a resource manually.
The problem that I have is little more complex but it can be minimized
to the above (i.e., I can solve the above by assigning the resources
manuallly and figuring out the most optimized allocation), but w/ a
large number of tasks/resrouces, automated optimization assignment is
needed (I am looking for something like a allocating a resource from a
group or a pool - but it seems like the concept of "pool" is used for
sharing of resources among project files and not for optimial
allocation problems)
equivalent in skills. Each task requires one resource only (no
sharing). There are depedencies among the tasks. Is it possible for
MS Project to figure out the best task-resource allocation to optimize
for the earliest project finish time w/o me having to assign each task
to a resource manually.
The problem that I have is little more complex but it can be minimized
to the above (i.e., I can solve the above by assigning the resources
manuallly and figuring out the most optimized allocation), but w/ a
large number of tasks/resrouces, automated optimization assignment is
needed (I am looking for something like a allocating a resource from a
group or a pool - but it seems like the concept of "pool" is used for
sharing of resources among project files and not for optimial
allocation problems)