V
Vadim Malyshev
Hello all,
Does MS Project have mechanism to automate change resources usage during
resource leveling procedure?
For example I have to write two documents and approve it. The approving
requires 15% of my time and duration in 5 days. The document witting require
5 days if I spend 100% of my time.
So I enter the following tasks:
1. Writing document 1 – 100%, 5 days
2. Approving document 1 – 15%, 5 days, depended of task 1
3. Writing document 2 – 100%, 5 days, depended of task 1
4. Approving document 2 – 15%, 5 days, depended of task 3
I want MS Project allocate my time for full time work as soon as possible,
so I want to get the following resource usage:
1. First 5 days – Writing document 1 – 100% full time
2. Second 5 days – 15% Approving document 1, and 85% Writing document 2
3. Later: 100% work in writing document 2, and after that approving document 2
I want to specify this strategy in my tasks, but I can’t do it. Each set of
task priorities and limits values get other scheduling (of cause I can
manually to specify my scheduling but it not likely for me).
Can anybody help me? How I can specify my tasks properties to get my
schedule strategy?
Does MS Project have mechanism to automate change resources usage during
resource leveling procedure?
For example I have to write two documents and approve it. The approving
requires 15% of my time and duration in 5 days. The document witting require
5 days if I spend 100% of my time.
So I enter the following tasks:
1. Writing document 1 – 100%, 5 days
2. Approving document 1 – 15%, 5 days, depended of task 1
3. Writing document 2 – 100%, 5 days, depended of task 1
4. Approving document 2 – 15%, 5 days, depended of task 3
I want MS Project allocate my time for full time work as soon as possible,
so I want to get the following resource usage:
1. First 5 days – Writing document 1 – 100% full time
2. Second 5 days – 15% Approving document 1, and 85% Writing document 2
3. Later: 100% work in writing document 2, and after that approving document 2
I want to specify this strategy in my tasks, but I can’t do it. Each set of
task priorities and limits values get other scheduling (of cause I can
manually to specify my scheduling but it not likely for me).
Can anybody help me? How I can specify my tasks properties to get my
schedule strategy?