Automatic Reallocation of Resources

F

Flewbie

My question is: Is there a way to level a project plan so that overallocated
resources are replaced with underallocated resources across the entire
project plan automatically? The leveling that I have tried seems to either
add delays to the timeline pushing back the end time or splits the task or
doesn't allow the subsequent task to start immediately upon completion of the
previous . What I want is for the overallocated resource to be removed from
the task and to have an underallocated resource assigned instead. The catch
is I don't want to have to do it manually for each resource.
 
M

Mike Glen

Hi Flewbie ,

Welcome to this Microsoft Project newsgroup :)

No :) Levelling only delays tasks where there is overallocation, nothing
more. How would Project know which resource to use to fill in the gaps?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 