Automatic resource leveling, does not work in EPM

K

K. R. Dixit

I have been using Microsoft Project for a long time. Recently, started using
EPM.
While doing automatic resource leveling, I observed that, it does not work
for Enterprise Resources. It works only for local resources.

I have reported this problem to Microsoft, India representative, but there
is no response.

If someone has faced this problem, and found some solution, please let me
know.

Regards,
 
G

Gérard Ducouret

Hello,

Did you open every project concerned by the resource leveling ? This feature
doesn't work on closed plans.

Gérard Ducouret
 
K

K. R. Dixit

I tried it on different projects, which are live.
All projects I faced same problem. Leveling works for local resources, but
does not work for Enterprise Resources.
Rgds,
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top