[MSP2002 and server 2002] I have added tasks to an existing schedule and then
rebaselined (to baseline 1) to track the additions as agreed and not
"variances". The Estimate at complete (EAC) field updates properly, but the
budget at complete (BAC) field does not update, nor does the summary task
assocuited with the added tasks. I used the correct (new) baseline in my EVA
calculations, so does anyone have any ideas how I can get teh BAC field to
update properly? Thanks,